Where in parallel systems, the right screen 0.0 corresponds to:
Paral. ---, address of each UPS with three characters, in the
example is 002.
Out.SW ---, the position of the output switch of the UPS
and/or switchgear panel board, with two status ON and OFF
(the auxiliary contact of the output switch in the output panel
board has to be connected according to the instructions of
section 5.2.9.2.).
• If the following alarm message appears on the LCD Control
Panel ...
MAINS PHASE ROT.
UPS START INH.
... also an audible alarm will beep in each equipment with the
message in the screen and the affected UPS/s not be able to be
started up, due to the wrong input phase rotation.
If it happens in only one UPS of the parallel system, turn
«Off» the input switch (Q1a) of the corresponding equip-
ment and the one in the switchgear panel board. Swap two
phases of the input terminals of the UPS leaving the connec-
tions in the same order as the rest of the equipments and
repeat the start up procedure described up to now.
If it happens in all equipments of the parallel system, turn
«Off» the input switch (Q1a) of each UPS and input switches
of the switchgear panel board, swap two phases in the input
terminals of the switchgear panel and repeat the start up pro-
cedure described up to now.
• In equipments or systems with separate static bypass line SLC
CUBE3+ B:
Turn the bypass switches from panel board «On».
Turn the bypass switches (Q4a) of each UPS to «On».
CONTROL & STATUS
OF THE UNIT
screen 1.0
(ESC)
(ESC)
Fig. 43. Diagram, start up/shutdown procedure.
120
screen 4.*
()
UPS ON STAND-BY
()
<ENT> TO START
screen 1.1
(ENT)
<ENT> TO CONFIRM
<ESC> TO CANCEL
screen 1.2
(ENT)
UPS RUNNING
<ESC> TO STOP
screen 1.3
(ESC)
<ENT> TO CONFIRM
<ESC> TO CANCEL
screen 1.4
(ENT)
• If the following alarm message appears on the LCD Control
Panel ...
... also an audible alarm will beep in each equipment with the
message in the screen and the affected UPS/s will not be able to
be started up, due to the wrong bypass phase rotation.
If it happens in only one UPS of the parallel system, turn
«Off» the bypass switch (Q4a) of the corresponding equip-
ment and the one in the switchgear panel board. Swap two
phases of the bypass terminals of the UPS leaving the con-
nections in the same order as the rest of the equipments and
repeat the start up procedure described in the three previous
steps.
If it happens in all equipments of the parallel system, turn
«Off» the bypass switch (Q4a) of each UPS and bypass
switches of the switchgear panel board, swap two phases
in the bypass terminals of the switchgear panel and repeat
the start up procedure described in the three previous steps
up to now.
• At this point, with no active alarm, green LED of Input Voltage
OK (a) (see Fig. 42), should light in all UPSs.
• Start up the inverter, by means of the keypad (3) (see Fig. 42). In
parallel systems make the procedure equipment by equipment
the first time or after complete shutdown, in order to establish
the communications among each unit of the system.
From main screen press () key to access to «CONTROL AND
STATUS OF THE UNIT» submenu (screen 1.0), and then press
() key. The screen 1.1 will be displayed, asking you to start the
equipment up by pressing (ENT). Do so, and then validate the
operation by pressing (ENT) again. See the diagram of Fig. 39.
()
BATTERY TEST
()
<status>
screen 1.5
Screens 1.1 and 1.3 are alter-
nated in the diagram, depen-
ding on the status of the
equipment.
The same happnes with the
screens1.6 and 1.8. Depen-
ding on the Smart Eco-mode
status, they are swapped.
BYPASS PHASE ROT.
UPS START INH.
screen 4.*
()
SMART ECO-MODE
()
<ENT> TO ACTIVE
screen 1.6
(ENT)
<ENT> TO CONFIRM
<ESC> TO CANCEL
screen 1.7
(ENT)
SMART ECO-MODE
<ESC> TO DEACTIVE
screen 1.8
(ESC)
<ENT> TO CONFIRM
(ESC)
<ESC> TO CANCEL
screen 1.9
(ENT)
USER MANUAL
(ESC)