Report prepared for Guillaume Thibodeau-Fortin (Stove Builder International Inc.) on
6/17/2019 7:40:40 AM
1 - MANUAL ENGLISH
7. Install a 90 degrees elbow facing out from the wall and then attach a 45 degree elbow facing
towards the ground. The termination of the vent must include a spark arrester, fastened to the 45
degrees elbow.
8. Sealed outside wall thimbles with high temperature waterproof silicone sealant.
3.5.3 Through Roof Installation
1. Position stove following clearances given in
Section
Combustibles and following vent manufacturer's
instructions.
2. Install a stove adapter or a stove adapter tee
onto the appliance flue collar. If necessary, use a
horizontal additional length between the flue
outlet and the tee.
3. Drop the plumb line over the center of the tee
outlet and mark location on the ceiling.
4. Cut a hole for appropriate ceiling support. Frame
rough opening.
5. Install ceiling support and the first vent section
as per vent manufacturer's instructions.
6. Install a firestop radiation shield on any
subsequent ceiling/floor, except for the attic
where an attic insulation shield is required.
7. Run the necessary section of vent vertically so
the rain cap exceeds the highest point of the roof
at least 24" in United States and at least 36" in
Canada.
8. Install roof support.
9. Install roof flashing and rain cap as per manufacturer's instructions. If necessary, install a storm
collar.
Cambridge II and Osburn 3000C Pellet Stove Installation and Operation Manual
Stove Builder International Inc. | 48202 | Rev: May 31 2019 10:15AM | Uncontrolled Copy
(19 OF 91)
3.2
Minimum
Clearances
to
19
Page 26 of 864