Commissioning
EN
7
Commissioning
Requirements
28
The following chapter describes the basic procedure for first time or re-
peated putting into operation of the generator. Follow the working steps de-
scribed below when you put your generator into operation for the first time
or restart it again after transporting it.
NOTICE!
For start-up and operation of a generator on building and assembly sites,
Deutsche Gesetzliche Unfallversicherung (DGUV) in DGUV Information
203-032, the May 2016 edition, requires observance of special protective
measures and behaviour regulations.
We also urgently advise observance of relevant DGUV information under
comparable operating conditions.
You must carry out the following preparatory steps after you have un-
packed your generator from the delivery packaging and are going to run it
for the first time:
The generator must be fully unpacked.
Suitable engine oil must be ready for use (see Chapter 9.3.1 ).
Suitable fuel must be ready for use (see Chapter 7.3 ).
1. Undo the bolts in the engine's side maintenance cover
2. Remove the cable tie from the 12V cable
3. Plug the plug and coupling together (see
the starter battery.
4. Fill the engine with the suitable engine oil (see Chapter 9.3 ).
The generator is now ready to be started.
Fig. 7-1 Initial start-up
.
), to make the power supply from
and then open it.