START-UP AND STOPPAGE

Read the technical documentation
Before installing and using the equipment, ensure you have read and fully
understood the instructions contained in this manual and the remaining support
technical documentation.
Additional information
If the information outlined in this manual is not exhaustive enough, please contact the
manufacturer of the device, whose details are available in the "Contacts" section.
External shut-off devices
All the following procedures refer to BCB and BCBS shut-off devices and are only
valid if these devices are installed (externally or internally) and relating to auxiliary
contacts appropriately cabled to the specific terminals.
5.1

PRELIMINARY TESTS

Before initiating the start-up procedure, check that:
➢ all the installation and connection works were carried out to standard;
➢ all the power and control cables are correctly and firmly connected to the specific
terminal boards;
➢ the ground conductor is correctly connected;
➢ the battery polarity is correct and the voltage within the operating values;
➢ the cyclic direction of the network is correct and voltage in tolerance with the
operating values;
➢ the "EPO" emergency stop button, if installed, is not pressed (on the contrary, bring it
to the rest position);