15. The production reservoir is fitted with a 20 mm diameter air intake
16. The unit is electrically protected by a 30 mA max. differential circuit breaker
17. The earth is properly connected
12.2 POST-COMMISSIONING CHECKS
1. General visual checks of all seals
2. Check of the hydrogen degassing
3. Hardness analysis of the water between the water softener and the ECO MX NANO electrolyser
4. Regular checks of the brine concentration in the ECO MX NANO electrolyser
5. Test the regeneration witch (optional)
6. Test the hydrogen detector (optional)
7. Test the pressure switch
8. Test the salt level in the water softener (optional)
Completed by:
Company:
Date of first commissioning:
At:
12.3 coMMIssIoNING Data sHEEt
Intervention type.
A. Commissioning
B. Service
C. Maintenance
D. Breakdown intervention
Date of visit:
Operating hours:
Mains water hardness:
Voltage measured:
Current measured:
Production concentration measured:
Quantity of salt added:
Visual check of seals:
Visual check of production reactor:
Visual check of degassing pipes:
Inspection of pre-filter fitted upstream to the unit:
62
Technical manual ECO MX NANO electrolyser code EN_P0011183 - Rev 7 - 19/04/2019
Signature: