Design Guide - Dual Integrated Installation
DUAL INTEGRATED INSTALLATION SPACE
Water And Electrical Locations
Electrical and water supply must be located as shown.
The Cutout Depth Must Be 25"
Cutout is based on installation of 2 Single Door products
with a left-and-right hand door swing.
Heater Unification Kit ZKMV required.
Product Clearances
These units are equipped with a 2-position door stop.
The factory set 115° door swing can be adjusted to 90° if
clearance to adjacent cabinets or walls is restricted.
Refer to Dim A on page 6 for clearances needed for door
swing.
REFRIGERATOR/FREEZER LOCATION
Do not install the refrigerator/freezer where the tem-
perature will go below 55°F (13°C). It will not run
often enough to maintain proper temperatures.
Do not install the refrigerator/freezer where
temperatures will go above 100°F (37°C). It will not
perform properly.
Do not install the refrigerator/freezer in a location
exposed to water (rain, etc.) or direct sunlight.
Install it on a floor strong enough to support it fully
loaded.
HARDWARE SUPPLIED (per unit)
• Odor filter (if equipped)
• Fresh filter (if equipped)
• 2 Anti-Tip brackets
• Lag screws
• Tapcon screws
• 1/4" hex screws
• Panel installation templates
• 2 Hinge limiter pins
• Door Hardware Kit
• Toe kick magnet
31-1000708 Rev. 4
Additional Specifications
• A separate 115 volt 60Hz., 15 or 20 amp power supply
is recommended for each product. An individual
properly grounded branch circuit or circuit breaker is
recommended. Install a properly grounded 3-prong
electrical receptacle recessed into the back wall.
Electrical must be located on rear wall as shown.
• Water line must be located on the back wall as shown.
The water line should be 1/4" O.D. copper tubing or
QuickConnect kit
TM
(WX08X10006) between the cold
water line and water connection location, long enough
to extend to the front of the unit (8' [2.4m]). Installation
of an easily accessible shut-off valve in the water line is
required.
• A minimum of 6" finished return matching cabinet
exterior is recommended on interior on all sides and
top at front of opening.
• Installations with 6" (15.2 cm) or less between units
require Heater Unification Kit.
TOOLS AND MATERIALS REQUIRED
• Metal shears (recommended)
• #1, #2 Phillips screwdriver
• Flathead screwdriver
• Putty knife (recommended)
• Measuring tape
• Drill and 1/16", 5/64", 3/16", 1/2" bits
• 5/32" concrete bit (if installing anti-tip into concrete)
• 1/4", 3/8", 7/16" driver/socket
• 7/16" open wrench
• T10, T20, T30 driver/bit
• 1/8", 1/4" hex driver (allen wrench)
• Level
• Water shut-off valves (optional but recommended)
• 8' waterline (one per unit requiring water hookup)
• Masking tape
• Rubbing alcohol
• 10" Adjustable wrench
• Center punch
• Heater Unification Kit (ZKMV)
• Stainless Steel Door Kits (if applicable)
• Custom panels for doors (if applicable)
• ZKPN (If applicable)
• Handle Kits (if applicable)
• Small Rachet 1/4" or 3/8"
• 90° Right Angle Driver or a minimum 8" long Phillips
bit extender
47