The individual connection jobs are listed in the following table and in the connection diagrams on pages 27 and 29. The ex-
planations in chapter 8, Electric switch unit, must also be heeded (position of the control elements, view of the inside of the
switch unit).
SINGLE SYSTEM- Heed safety instructions!
Work to be done
Battery connection
(rechargeable batteries up to year 12/09
Mains connection
Motor supply cable
Motor temperature sensor
Level measurement
All manuals and user guides at all-guides.com
5. Electrical connections
Switch unit
Both batteries (2 x 9V block) must
from model year 01/10
be connected on the board.
• Connect the mains supply cable L1
)
/ L2 / L3 / N / PE at the terminal
block using screw connection.
• N and PE always have to be
connected.
• The mains supply cable must have
an all-pole main switch on the in-
stallation side that is clearly assig-
ned to the control.
• The pre-fuse prescribed on the in-
stallation side must not exceed 16
A per phase.
• The control can be damaged or de-
stroyed if connection is not carried
out correctly.
• Connect the motor supply cable
U/V/W to the connector in the right di-
rection in the lower screw terminals
T1 / T2 / T3. The direction of rotation
of the motor must be heeded.
• PE must be connected with TF1
and TF2 to the terminal block on
the board underneath the motor
protection switch.
• Wire 4 of the motor supply cable
must be connected to the lowest
terminal of the terminal block TF2
TF1.
Wire 5 of the motor supply cable
must be connected to the central
terminal of the terminal block TF2
TF1. The input TF2 is bridged using
a 2-pole jumper, i.e. the central ter-
minal is doubly occupied. Jumper
must not be removed!
Connection to the pressure sensor
The transparent air hose must al-
ways be routed rising to the switch
unit. The air hose must be screwed
tight to the connection provided on
the switch
57
• The rechargeable battery (1 x 9V block) must
Switch unit
up to model year 12/09
be inserted into rechargeable battery fixture.
• Connect the mains supply cable L1 / L2 / L3 /
N / PE to the upper level of the grey mains
connection terminal block, heeding markings
(printing on the board).
• N and PE always have to be connected.
• The mains supply cable must have an all-pole
main switch on the installation side that is
clearly assigned to the control.
• The pre-fuse prescribed on the installation side
must not exceed 16 A per phase.
• The control can be damaged or destroyed if
connection is not carried out correctly.
• Connect the motor supply cable U/V/W to the
ABB connector B6-30-10 left of the motor pro-
tection switch in the right direction in the lower
screw terminals T1 / T2 / T3. The direction of
rotation of the motor must be heeded.
• Connect PE to the lower level of the grey
mains connection terminal block, heeding the
markings (printing on the board).
• Input TF: Wire 4 of the motor supply cable
must be connected on the right at TF input,
wire 5 on the left at TF input.
• Input E7: The jumper must be left.
Level inputs (ON/ALARM)
• The cable must always be routed rising to the
switch unit.
• The cable ends of the pressure level switch
must be connected to the respectively marked
terminals (white wire on the right, brown wire
on the left to "on" input, green wire on the right
and yellow wire on the left to "alarm" input).

Publicité