Pipe Work; Electrical Connection / Earthing - salmson S Serie Manuel D'installation Et Mise En Service

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

  ENGLISH  
 
7.2 PIPE WORK 
Pump connection flanges are plugged to avoid any contamination during 
transport and storage. Protective covers should be removed only before 
installing  the  pump  in  the  piping.  Remove  dust  before  removing  the 
covers  from  pump  flanges.  Especially  for  new  pipe  work  :  clean 
thoroughly piping before connecting it to the pump. 
 Remove protective covers 
 Add flange gaskets 
 Fasten suction pipe 
 Fasten discharge pipe 
 
No stress must be applied to the pump casing by the pipe work. If 
 
excessive,  those  forces  and  moments  cause  misalignment, 
overheating of bearings, coupling wear, vibrations and possible failure or 
explosion of pump casing. 
After  replacement  of  a  pump  or  during  connection  of  pipes  to 
 
pump flanges, never use pump flanges as a support to pull or push 
the pipe works. 
 
The  axial  displacement  of  expansion  coupling  (if  installed)  should  be 
limited. Use tie rods as recommended by the manufacturer. 
 
Two designs are possible for the suction line : positive suction head and 
suction lift operation. 
 
Positive suction head operation : 
Nominal  diameter  of  the  pipeline  is  often  larger  diameter  than  pump 
suction flange. Unequal nominal diameter should be compensated by an 
eccentric  transition  part.  It  is  recommended  to  install  a  straight  pipe 
before  the  pump  inlet  (size  L  should  be  2  to  3  times  the  pipe  nominal 
dimension).  The  suction  line  should  be  laid  with  a  downward  slope 
toward the pump. 
 
Suction lift operation : 
Nominal diameter of the suction pipe must be equal or a size larger than 
the pump suction flange diameter. Pipe inlet should be set below lower 
liquid level. Install a strainer with foot valve to prevent priming loss. The 
strainer  will  be  installed  far  enough  from  the  pit  bottom  to  avoid 
excessive suction head losses and particles intake. Ensure there is no air 
intake  along  the  suction  pipe  and  that  the  suction  pipe  is  inclined 
upwards towards the pump inlet. Avoid air pocket creation. 
 
Suction  line  should  be  airtight  and  as  short  as  possible.  Use  of  large 
radius  bends  should  be  preferred.  If  possible  the  nominal  diameter  of 
suction  pipe  will  be  the  same  as  pump  nominal  diameter.  The  size  of 
pipe will be selected to limit flow speed to 2m/s. A straight pipe (length 
= 2 times the pipe diameter) will be installed on pump suction side. 
During  pump  priming  period  air  contained  in  the  suction  pipe  is 
eliminated and liquid is lifted up to suction flange level. 
 
 
When  suction  pipe  is  full  of  liquid  the  pump  is  acting  like  a  standard 
centrifugal pump. 
Priming  time  will  increase  if  a  larger  pipe  diameter  is  used  or  if  pipe 
length  is  increased.  Any  air  intake  along  this  pipe  will  delay  or  avoid 
pump priming. 
 
Check  that  pump  required  NPSH  (NPSH
available NPSH (NPSH
 
Discharge pipe : 
During  priming  time,  air  contained  in  suction  pipe  is  pumped  through 
the  pump  to  the  discharge  pipe.  Free  exhaust  of  this  gas  to  the 
atmosphere should be possible. 
  If  this  requirement  cannot  be  met,  a  vent  pipe  connected  before  the 
NRV  and  going  back  to  the  pit/sump  or  an  automatic  air‐vent  valve 
should be installed. 
If an explosion hazard exists, check that the area around the outlet 
of this venting pipe is identified as an ATEX zone. 
 A vent pipe or an automatic air vent valve must be installed ahead of 
the non‐return valve. A motorized valve can be used to close vent pipe 
and avoid recirculation of fluid during normal operation. 
 Nominal diameter of discharge pipe should be chosen to ensure a max 
flow speed of 3m/s. 
 
Filter/strainer : 
If  required  a  filter  can  be  installed  before  the  pump  intake.  To  ensure 
proper working of pump the equivalent exchange surface of the strainer 
should be 3 time the pipe sectional area. 
Clogging state of filter/strainer should be checked regularly. 
 
 
Valves : 
It is advised to install isolating valves on suction and  discharge side for 
maintenance purpose. Those valves should be of large passage type and 
could be locked in position. 
Isolating  valve  on  suction  side  will  not  be  connected  directly  to  pump 
suction flange. 
 
Auxiliary piping : 
For  most  of  applications  a  single  mechanical  seal  is  used.  If  the  sealing 
must  be  equipped  with  auxiliary  equipments,  check  that  there  are  no 
leakages and that direction of flow is respected. 
 
Single mechanical seal with quench :  
External piping system or raised tank should be installed in the state of 
the art. Pressure in the quench should not exceed 0,35 bar. 
 
Single mechanical seal with external flushing :  
Flushing fluid should be pressurized at 0,5 / 1 bar above pump discharge 
pressure. 
 
After pipe work is done turn the pump shaft by hand and check that it 
turns freely. If it appears that it is difficult to turn the pump shaft, then 
check  forces  applied  by  piping  to  pump  casing.  Installation  of  piping 
should be done again. 
 
7.3 ELECTRICAL CONNECTION / EARTHING 
Check  that  motor  winding  corresponds  to  site  electric  power 
supply characteristics before electrical connections are performed. 
Connecting  a  230/400V  motor  on  a  400V  power  supply  or 
14
 
)  is  lower  than  system 
R
). 
A

Publicité

Chapitres

Table des Matières
loading

Table des Matières