Commissioning
4.1
Tests before the first commissioning
Mechanical functional check
Sensor and actuating element must not touch when the protective
device is closed.
Distance between sensor and actuating element with protective
device closed min. 1 mm (cf. Fig. 2).
Electrical functional check
On connection to 110 V AC or 230 V AC operating voltage: Prior to
switch on, check whether the voltage selector switch is set
correctly.
4.1.1
Check stop function
Close all protective devices.
Start machine.
Open first protective device.
Check whether the machine stops when the protective device is
opened.
Close all protective devices again, start machine and perform the
same procedure individually with each protective device.
4.1.2
Check start function
Switch off machine.
Open first protective device.
Start machine.
The machine must not start with a protective device open!
Perform this procedure for each protective device/sensor. Close all
protective devices except one, start machine and check each
sensor individually in this manner.
4.1.3
Check delay time
When the delayed output 57/58 is used, the delay time must be
checked.
The time set must be greater than the time determined in the risk
analysis.