Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 43
38 / 136
5

Commissioning

5.1
Commissioning tasks
Check whether the steps explained in the chapter on
assembly have been carried out correctly.
Clear any building waste from the tank if necessary.
Connect the system to the power supply. Lift the float
switch to check whether the submersible pump starts
automatically.
With the connection of the cable(s) to the power supply,
the system is ready for operation.
Dry running of the pump must be avoided!
016-083

Publicité

Table des Matières
loading

Table des Matières