5
Commissioning
Observe EN 12056-4 for the commissioning.
5.1
Checking the system
Check the following points before commissioning:
Correct installation of the pump(s)
Fixing of all removable components
Leak-tightness of the system
Mains voltage (max. deviation ± 10 %)
Correct fit of the elements for level detection
System is clean and free of building debris
5.2
System commissioning
Always avoid the pumps running dry (air is drawn in) for longer periods (> 30 seconds). The pumps can become dam-
aged.
Do not activate pumps in manual operation if the system tank is not filled to at least minimum level.
5.3
Commissioning the system (Mono with float switch)
The system is made ready for operation by connection to the mains power supply.
System is ready for operation.