14
Decommissioning, dismantling, environmental protection
Personnel:
Protective equipment:
DANGER!
Risk of injury due to the disregard of the specified personal protective
equipment (PPE)!
For all disassembly work, please respect the use of the PSA which is
specified on the product data sheet.
14.1
Decommissioning
DANGER!
The procedures described here may only be carried out by skilled
personnel as described at the start of the chapter, this may only be done
using PPE.
To take the equipment out of operation, proceed as follows:
1.
Before carrying out any subsequent work, completely cut off the electrical supply first
and secure it against unintentional switch-on.
2.
Relieve internal pressure of the pump and line pressure in the metering system.
3.
Drain off metering medium from the entire system without leaving any residue.
4.
Drain and remove operating and auxiliary materials.
5.
Remove the remaining processing materials and dispose of them in an
environment-friendly way.
Decommissioning, dismantling, environmental protection
n
Service personnel
n
Specialist
Protective gloves
n
n
Chemical-resistant protective gloves
n
Protective eyewear
n
Safety shoes
253
417102269 Rev. 2-08.2020