5.3.2.4
Installation steps for ground installation without tilt correction
Minebea Intec
2. Employ the appropriate lifting tool to slightly lift the container or every position with
load cell (7) individually so that the pendulum base (3) can be turned and the
threaded holes in the pendulum base can be aligned with the holes in the
substructure (21).
3. Insert the O-ring (15) into the groove of the pendulum base.
4. From below, screw the pendulum base (3) to the substructure (21) screws (22,
washer 4×; 23, screw 4× M8). Always comply with the strength classes and tightening
torques of the connector elements (see Chapter 5.2).
NOTICE
Never vertically straighten up a tilted pendulum base by pulling on the screws.
It is essential to observe a tolerance of ≤1 mm (see Chapter 5.1.1).