5 Installation
EN-23
NOTICE
The gasket and the O-rings are delicate mounting parts.
Do not use any sharp-edged tools.
NOTICE
No leak-tightness of the contact surfaces present.
The contact surfaces between the adapter plate and vessel foot/lug as well as
between pendulum base and substructure/bottom must be clean and level to
ensure a reliable seal.
Note:
The load cell is packaged together with the pendulum pin including O-ring and gasket.
The pre-mounted pendulum base is delivered with a separately-packaged O-ring.
NOTICE
Welding or lightning strike current lowing through the cell can damage it.
All electrical welding on the weighing system must be inished before mounting the load
cells.
When installing the load cell, immediately bypass the load cell with the lexible
copper strap provided for this purpose.
If subsequent electrical welding needs to be performed near the load cell,
-
disconnect the load cell cables.
-
bypass the load cell carefully.
-
make sure that the grounding clamp of the welding set is itted as closely as possible
to the welding joint.
The following must be observed during installation:
-
Do not lift or transport the load cell by pulling on the cable.
-
Avoid shock stress (falling down, hard shocks).
NOTICE
Changes of temperature >15 K/h may inluence the measuring accuracy.
Make sure to protect the load cells from direct heating or cooling efects (sun, wind,
heat radiation, fan heaters), e.g., heat protection screens or heat protection
housings are to be installed if necessary.
NOTICE
Force shunts may cause measuring errors.
All incoming and outgoing lines (hoses, pipes, cables) must be coupled to the
measured object as lexibly as possible.
Hygienic Weighing Module Novego®