Minebea Intec Novego Manuel D'installation page 21

Masquer les pouces Voir aussi pour Novego:
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

5 Installation
5.1.2.1
For pendulum base without tilt correction
EN-19
NOTICE
No leak-tightness of the supporting/sealing surface present between pendulum
base and bottom.
Leak-tightness between the pendulum base (2) and bottom (4) must be ensured
using O-ring (3).
.
The load distribution on the available load cells must be as even as possible to
prevent overload of the individual load cells.
.
Use the drilling template to generate the drilling pattern of the pendulum bases (see
Chapter 4.5) according to the weighing system arrangement.
.
For this purpose, place the template on the ground in order to the set the drill holes
for the threaded anchor and mount it.
.
The contact surfaces of the pendulum bases (2) and the contact surfaces of the vessel
feet (1) must be arranged in parallel.
The maximum permissible misalignment and the maximum allowable misalignment
must be strictly observed, see Figure!
Hygienic Weighing Module Novego®
Minebea Intec

Publicité

Table des Matières
loading

Table des Matières