5
Commissioning
5.1
Mechanical commissioning
Connect water supply if necessary.
Fill separator with cold water up to the static level (level of the outlet).
Have a general inspection carried out (during initial commissioning and then every 5 years).
Give safety instruction.
File all records in the log book and document required disposal cycle.
All documents must be kept available at the system. The local supervisory authority can ask to examine the documents.
Tightness of the pipe connections
Before commissioning, a leak test must be performed on all on-site connections. The pre-assembled connections have
undergone a leak test at the factory and only need to be tested again if the connections have been dismantled e.g. for easier
installation.
5.2
Electrical commissioning
5.2.1
Versions: EasyClean free Standard and EasyClean free Direct
No further electrical testing is required.
5.2.2
Versions: EasyClean free Mix and EasyClean free Auto Mix
EasyClean free Mix
See the installation and operating instructions 016-271 Connect 400 V Mono control unit for grease separators
EasyClean free Auto Mix
Item
Assembly/functional element
no.
(1)
Power LED
(1)
Alarm button and alarm LED
(3)
ESC, Arrow buttons, OK,
(4)
Display
(5)
Level exceedance LED
(6)
Manual Operation button (no function) and Man-
ual Operation LED
During initialisation, the following input is expected:
|Language|
|Date / time|
|Nominal size |
|Number of pumps |
Language
► Use the cursor keys to select the language and confirm
with OK.
► Press OK.
|Date / Time|
Menu
Date / time
► Set the respective flashing figure in date and confirm with
OK.
► Press OK.
► Set the respective flashing figure in time and confirm with
OK.
► Press OK.
|Nominal size|
Menu
62 / 132
appears.
appears.
Installation and operating instructions
016-673