6.4. TO START UP THE UPS OF PREVIOUS
SECTION.
For units with alphanumerical display.
Start up the inverter by means of the keypad of the control
ˆ
panel (3) (see Fig. 42).
From main screen press () key to access to «CONTROL
AND STATUS OF THE UNIT» submenu (screen 1.0), and
then press () key. The screen 1.1 will be displayed,
asking you to start the equipment up by pressing (ENT).
Do so, and then validate the operation by pressing (ENT)
again. See the diagram of Fig. 39.
The UPS will take about 30 seconds to be operative again.
For units with touch screen.
Start up the inverter of the equipment, to do it proceed as
ˆ
follows:
Touch over the «Status and control» icon
Touch over the «Start/Stop UPS» icon
The following «Pop up» message will be displayed. It
asks to the end-user if it he is sure about his selection
Are you sure ?
Confirm the action by touching over the
YES
NO
«YES».
Turn the output switch (Q2) of the UPS, to position «On».
6.5. COMPLETE SHUTDOWN OF THE UPS
OR SYSTEM.
Shutdown the loads.
If the equipment or parallel system has an outgoing distribu-
tion, turn its switches «Off».
Shutdown the inverter of the UPS.
For equipments with alphanumerical display.
ˆ
Through the control panel keypad (3) (see Fig. 42) and
from main menu, press the key () to access to the
«CONTROL AND EQUIPMENT STATUS» submenu (screen
1.0), and next press the key (). The screen 1.3 will be
displayed, where to stop the equipment the key (ESC) has
to be pressed. Press the key and confirm the operation by
pressing over (ENT). See the diagram of Fig. 39.
For equipments with touch screen control panel.
ˆ
Touch over the «Status and control» icon
Touch over the «Start/Stop UPS» icon
The following «Pop up» message will be displayed, It
asks to the end-user if it he is sure about his selec-
Are you sure ?
tion
YES
NO
«YES».
In parallel systems is necessary to act over one of
them only.
Consider that the UPS or system is still supplying
output voltage through the static bypass.
USER'S MANUAL
Status & Control
Start / Stop
.
UPS
Status & Control
Start / Stop
.
UPS
. Confirm the action by touching over
Turn «Off» the output switch or switches of the panel board.
Turn the output switch (Q2) of the UPS or each equipment of
the system, to «Off» position.
Turn the battery switch, battery protection or both elements
«Off», considering both available topologies and the estab-
lished order:
Equipments with a single battery mechanism, either with
ˆ
a battery fuse holder switch or battery switch and labelled
in the figures of the present document as (Q3).
Equipments with two battery mechanisms, fuse holder
ˆ
switch (F3) and switch (Q3):
Battery fuse holder switch (F3) first.
1.
Next the battery switch (Q3).
2.
In parallel systems, repeat the process in each equipment.
For equipments with external battery cabinets, turn the fuse
holder switch of the battery cabinet/s (Q8) of each UPS to
«Off».
.
In equipments or systems with separate static bypass line SLC
CUBE3+ PS B:
Turn the bypass switch or switches of the panel board, to «Off».
Turn the bypass switch (Q4a) of the UPS or each equipment of
the system, to «Off».
Turn the input switch or switches of the panel board to «Off».
Turn the input switch (Q1a) of the UPS or each equipment of
the system, to «Off».
Break the input power supply of the switchgear panel. The
system will be completely deactivated.
Electrical discharge hazard. In case the battery
cabinets or racks are required to be disconnect from
UPS, wait several minutes (5 min. approx), till the electrolytic
capacitors have been discharged.
6.6. EMERGENCY POWER OFF (EPO)
BUTTON OPERATION.
Emergency Power Off (EPO) is equivalent to a complete shutdown:
UPS converter or all converters of the system are shutdown
(rectifier and inverter).
No power supply is supplied to the loads.
The emergency power off (EPO) function can only be activated
through the two pins terminal strip (X50). In a parallel system, it
.
is not needed to make more connections than the ones done in a
single equipment, because through the communication BUS, any
action over the button will affect to the complete parallel system.
SLC CUBE3+ PS UNINTERRUMPTIBLE POWER SOURCE
133