4.7.2
Operation
Starting initial commissioning
Language
747.431
✔ The check list for initial commissioning is displayed:
The default display language is English.
n
The Language entry is selected.
n
The check boxes are not selected.
n
———————————————————————————
NOTICES
When a check list item is called up the corresponding
n
check box is automatically selected.
The following items are only displayed when the use of
n
a reactive power characteristic curve is prescribed for
the country currently selected in the Country item:
–
Reac. pwr. ch. c. (type of reactive power character-
istic curve)
–
No. of nodes
–
1)
Node 1
–
1)
Node 2
–
1) 2)
Node n
–
Display char. curve
1)
: Is only displayed for reactive power characteristic
curve type Enter char. curve.
2)
: Is only displayed when no. of nodes has been set to a
value > 2.
Initial commissioning is completed by calling up the
n
Finish item.
Finish can only be performed when
n
boxes are selected.
———————————————————————————
1. Press rs to select a check list item.
2. Press SET to call up the item.
The items are described in detail below.
1. Press rs to select a display language.
2. Press SET. The language is adopted.
3. Press ESC. The check list is shown.
1)
all other check
GB
107