SMA Solar Technology AG
7
Commissioning
7.1
Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Commissioning a product in SMA Energy Systems
If the product is used in an SMA Energy System, the commissioning must be performed
according to the manual of the SMA Energy System. The procedure and the sequence may
differ from the steps described in this section.
• Commissioning an SMA Energy System (see system manual of the SMA Energy System).
Commissioning an inverter that is captured in a communication device
When the inverter is captured in a communication device, the communication device (e.g.
SMA Data Manager) is the unit for configuring the total system. The configuration is
transferred to all inverters in the system. The system password assigned via the communication
device is also the password for the user interface of the inverter.
• Commission the inverter (see Section 7.2, page 58).
• The initial configuration of the inverter is made via the communication device. The
configuration is transferred to the inverter and the settings of the inverter are overwritten.
• Deactivate the Webconnect function of the inverter via the Sunny Portal. This prevents
unnecessary connection attempts of the inverter with Sunny Portal.
Procedure
1.
Commission the inverter.
2.
Establish a connection to the user interface of the inverter.
There are various connection options to choose from for
this:
• Direct connection via WLAN
• Direct connection via Ethernet
• Connection via WLAN in the local network
• Connection via Ethernet in the local network
3.
Log into the user interface.
4.
Select the inverter configuration option. Please note that
the SMA Grid Guard code for changing the grid-relevant
parameters must be available after completion of the first
ten feed-in hours or installation assistant. You can request
the SMA Grid Guard code via the Online Service Center.
5.
Ensure that the country data set has been configured cor-
rectly.
6.
Make further inverter settings as needed.
Installation Manual
7 Commissioning
See
see section 7.2, page 58
see section 7.3, page 59
see section 7.4, page 63
Configuring the Inverter
Inverter user manual
Inverter user manual
SBSxx-US-10-IA-xx-14
57