8. Stick the terminal block into the slot
battery interface module in the inverter.
9. Ensure that the terminal block is securely in place.
10. Ensure that all conductors are correctly connected.
11. Ensure that the conductors sit securely in the terminal points. Tip: To release the conductors
from the terminal block, open the terminal points using a suitable tool.
12. Install switch in desired position (e.g. next to the inverter or as switch/outlet combination
optionally at short distance from the inverter (to max. 10 m (33 ft))).
13. Connect the other end of the cable directly to the switch.
6.7
Connecting Switch for black start (in battery-backup
systems)
The switch for black start is connected to the same jack as the switch for secure power supply
operation. Observe that the secure power supply operation is not available in battery-backup
systems.
Requirements for the conductors:
☐ Conductor cross-section: 0.2 mm² to 2.5 mm² (24 AWG to 14 AWG)
☐ The conductor type and wiring method must be appropriate for the application and location.
☐ Maximum length of conductors: 10 m (33 ft)
Procedure:
1. Ensure that the inverter is disconnected from all voltage sources (see Section 8, page 65).
2. Remove the sealing plug from the opening for connecting the switch for secure power supply
operation.
3. Insert the conduit fitting into the opening and tighten from the inside using the counter nut.
4. Attach the conduit to the conduit fitting.
5. Guide the conductors into the inverter.
6. Strip off the conductor insulation by min. 6 mm (0.24 in) to max. 10 mm (0.39 in).
7. Connect the conductors to the 2-pole terminal
blocks. Ensure that the conductors are plugged
completely into the terminal points up to their
insulation.
Installation Manual
on the
SBSxx-US-10-IA-xx-14
6 Electrical Connection
47

Publicité

loading

Ce manuel est également adapté pour:

Sunny boy storage 5.0-usSunny boy storage 6.0-us