Plast Coat 830
AutOMAtIC SPRAy LANCe
6.8
BeGINNING OF tHe SPRAyING PROCeSS
• Open the air tap (Fig. 16, 2) and material tap (Fig. 16, 1) at the
spray lance.
• Set the amount of material using the volume regulator (fig.
15, 3) and the amount of air by setting the air tap (Fig. 16, 2)
in order to achieve the corresponding spray pattern.
Increased material tap wear. Do not use the
material tap to set the material volume.
the delivery volume controller should be
used for this purpose.
6.9
eND OF tHe SPRAyING PROCeSS
• Close the material tap (Fig. 16, 3).
• Close the air tap (Fig. 16, 2).
Always close material tap at end of the
spray process.
PNeuMAtIC SPRAy LANCe
6.8
BeGINNING OF tHe SPRAyING PROCeSS
• Open material tap (1, Fig. 17) on spray lance.
• Set the amount of material using the volume regulator (fig.
15, 3) in order to achieve the corresponding spray pattern.
Increased material tap wear. Do not use the
material tap to set the material volume.
the delivery volume controller should be
used for this purpose.
6.9
eND OF tHe SPRAyING PROCeSS
• Close material tap (1, Fig. 17) on spray lance.
Always close material tap at end of the
spray process.
GB
commIssIonIng