Commissioning
Observe EN 12056-4 for the commissioning.
Always avoid the pumps running dry (air is drawn in) for longer periods (> 30 seconds). The pumps can become dam-
aged.
Never switch on the pump if the system tank is not filled at least up to the minimum level.
5.1
Displays, operating keys and their functions
(1)
Ready for operation LED (green)
(2)
Alarm LED (red)
(3)
LED system tank switch-on level reached (orange)
(4)
LED wastewater pump running (orange)
(5)
LED wastewater pump running (orange, only Duo)
(6)
Operation symbol
(7)
Switch off (acknowledge) alarm button
(8)
System tank symbol
(9)
Wastewater pump on (manual) button
(10)
Wastewater pump on (manual) button, (Duo only)
5.2
Commissioning the system
Initialising the control unit
Supply the control unit with mains power.
The initialisation starts and the 4 (Mono) or 5 (Duo) LEDs light up consecutively, a signal tone sounds and the wastewater
pump is switched on for a few seconds.
After successful initialisation, the control unit is ready for operation and the green LED (1) illuminates.
Functional check
Switch the system off (pull out mains plug).
Open the maintenance opening on the system,
Completely fill the system tank with water.
Restore the power supply to the control unit (plug in the mains plug).
The control unit will initialise.
The functional check is successful if the following proce-
dures are carried out as described:
The alarm level is triggered, the alarm LED (2) flashes
red, a signal tone is generated and the wastewater pump
starts to empty the system tank.
After reducing the level below the alarm threshold, the
alarm LED (2) extinguishes and the orange LEDs level
(3) and pump operation (4 and 5 (Duo)) light up until the
system tank has been emptied by the wastewater pump.
Visual inspection:
Once the wastewater pump has stopped running, only
a few centimetres of water should be left in the system
tank.
Screw tight the maintenance opening on the system.
The system is ready for operation