5.3
Preparing for maintenance work
–
Make sure that the inlet to the lifting station is not used during maintenance.
–
Make sure that the lifting station cannot be switched on accidentally during maintenance work. This applies in
particular if the control unit is in a different room to the system tank.
5.4
Maintenance jobs
5.4.1
Replace battery
•
Perform the work described in 5.1
•
Open the housing cover of the control unit and replace the battery
•
Screw down the control unit's housing cover, make a potential-free connection if necessary and perform a functional
check (see 3.9.2)
•
Change the battery once a year
5.4.2
Cleaning the lifting station
•
Lower the wastewater level in the system tank to a minimum. To do so,
run the wastewater pump in manual operation (see Chapter 4.6) until
the pump draws in air.
•
Bring the ventilation device <25A> on the backwater preventer <25>
into a horizontal position (as shown), the dammed up wastewater can
flow back from the pressure pipe into the system tank