• Remove the boom articulation locking rod (L) location
(W) (See page 5 fig. 3.b) and unlock the strut (C) to
fold the Davitrac™+ boom (D)
• Lock the boom transport locking system onto the
mast (M)
• Take Davitrac™+ off its base
Davitrac™+ is now folded up and ready for transport
(fig. 3.c).
5.3. Installing a bracket on the
Davitrac™+ mast
NOTICE
The Davitrac™+ mast may be equipped with a
variety of systems with a Tractel Davitrac™+ bracket
for Blocfor
R - Work winch - Scafor
®
When only one system is installed, it must be installed
at the rear of the mast:
• A Scafor
or work winch hoist is placed in the high
®
position (R) (See page 5 - fig. 4.a)
• The Blocfor
R fall arrest device is in the low position
®
(N) (See page 5 - fig. 4.b)
When several systems are installed, they must be
installed as follows:
• A Scafor
or work winch hoist is placed in the high
®
position (R) at the rear of the mast (See page 5 - fig.
4c)
• The Blocfor
R fall arrest device is in the low position
®
(N) at the front of the mast (See page 5 - fig. 4.c)
No other configuration is permitted.
Once Davitrac™+ is in place and unfolded.
1. Install the bracket on the Davitrac™+ mast (fig. 5).
Each bracket has a positioning rod that prevents the
chosen system from being set up incorrectly. Each
bracket must necessarily be fixed with the two rods
connected to the bracket.
Note: It is strictly forbidden to modify the anchoring
bracket supplied with the system in any way.
2. On the mast, choose the holes that correspond
to the holes on the bracket and fix it with the rods
(fig. 5).
3. Lock the bracket with the rods and locking pins
fastened to the bracket (fig. 5).
NOTICE
For each device with a bracket, the cable must
be routed over the appropriate transfer pulley on
Davitrac™+ (See page 11 - fig. 17).
5.4. Putting in place the cable on the
cable transfer pulley
1. Depending on the positioning of your system, route
2. Pull out the cable guide rod (fig. 4) fastened to the
3. Route the cable over the pulley appropriate for the
4. Replace the cable guide rod (See page 11 - Fig 17)
.
®
The cable may only be installed on the pulleys by an
operator who has read the installation instructions as
described in the manual.
When two systems are attached to the (See page 11
- Fig 17), make sure that the cables do not cross each
other.
5.5. Installing a fall protection device on
the anchor point of the Davitrac™+ head
The adjustable Davitrac™+ anchoring head is equipped
with a PPE anchor point and a lifting anchor point.
On the PPE anchor point of the head, any certified PPE
for 1 operator with a maximum weight of 330 lb. (150 kg)
and an average arrest force limited to a maximum of
900 lb (400 daN) can be connected to it.
Two fall protection systems must never be connected
to the same anchor point; do not connect a lifting
system to the PPE anchor point.
The connection with the PPE anchor point on
Davitrac™+ must be made using an ANSI Z359 or
CSA Z259 approved device. connector.
5.6. Installing a fall protection system
on the anchor point of the Davitrac™+
articulation plate
The Davitrac™+ articulation plate is equipped with two
PPE anchor points.
the cable over the transfer pulleys (See page 11 -
fig. 17).
adjustable anchoring head on the boom.
system.
a. Left side for the PPE pulley for Blocfor
page 11 - Fig 17)
b. Right side for Lifting Pulley for all hoists (Work
winch, Scafor) (See page 11 - Fig 17)
with its locking pin to lock the system.
NOTICE
WARNING
EN
R (See
®
25