INSTALLATION
4.1
Hydraulic connections
IMPORTANT: when selecting the installation sites of the various components, and before creating
the by-pass loops on the installation, make sure that the power cables of each of the components
are long enough to reach the electrical panel from the selected installation site.
In the plant room, create a by-pass loop, downstream from all other devices mounted on the hydraulic
circuit, to allow installation of the cell, the flow sensor and the acid dosing pump (if one is being installed).
The cell may be oriented vertically or horizontally, provided that the direction of flow indicated in the
diagram is respected.
To avoid the accumulation of air in the cell in the event that air enters the hydraulic circuit, the cell should
not be installed at a high point on the hydraulic circuit.
If installing an acid dosing pump, this should be located downstream just after the cell.
The by-pass should be designed such that acid injected to descale the cell (when filtration stops) remains
in the cell. In some configurations, this will require installation of a check valve.
The flow sensor should be positioned such that the acid used to descale the cell will not touch it.
A check valve can ensure this.
46/80
2021/02 - Indice de révision : E - Code : 29650
qty
Comments
To be mounted on the end of
1
the suction tube delivered with
the acid dosing pump
EES
EES Pro
X
X
X
X
TRAITEMENT DE L'EAU