Controls
See the operator's manual for complete descriptions of the
generator controls.
Operation
Automatic Operation Sequence
The generator's control panel houses a logic control circuit
board. This system constantly monitors utility power source
voltage. Should that voltage drop below a preset level,
control board action will signal the engine to crank and start.
When utility source voltage is restored above a preset
voltage level, the engine is signaled to shut down.
The actual system operation is not adjustable and is
sequenced by sensors and timers on the control board and
transfer switch, as follows:
24
Setting Exercise Timer
It is recommended to have the generator go through an
excercise cycle once every seven days. During this exercise
period, the unit runs for approximately 20 minutes and then
shuts down.
Refer to the Automatic Transfer Switch Manual for more
detailed information on the exercise timer.
Installation Inspection
Before placing the generator system into service, inspect the
entire installation carefully.
This completes the installation and start-up instructions.
The operator's manual provides full details on Operation,
Maintenance and Troubleshooting for this generator system.