1. Main screen. Current and daily yield.
This section contains:
– Actual output power (kW)
– Yield of the current day (kWh)
– Total yield (kWh)
– Current date and current time
– Operating mode (#)
2. Inverter information. This section contains:
– Device type and name of the inverter
– Inverter serial number
– IP Address
– Serial number of the SMA Inverter Manager
– Software version of the inverter
3. Actual values This section contains:
– PV voltage and current
– Phase-to-phase voltages
– Phase currents
– Grid frequency

6.2 Initial Setup via LCS-Tool

The inverter and the SMA inverter manager must be
commissioned via the local commissioning and
service tool (LCS-Tool). Commissioning is necessary
before the inverter starts feeding into the utility grid.
The LCS too enables the selection of predefined
country data sets for different utility grids.
Customer-specific country data sets can be provided
by SMA and imported via the LCS-Tool (see
installation manual of the SMA Inverter Manager /
SMA Digital I/O Box / LCS-Tool).
Installation Guide
6.3 Switching on the DC
Load-Break Switch
Switch on the DC load-break switch at the inverter
and, if available, at the PV array junction box.

6.4 Commissioning

The inverter starts automatically if sufficient solar
irradiation is available. Starting takes a few minutes.
During this period, the inverter performs a self-test.
Observe the specified sequence for commissioning
for the respective device type.
STP 60-10 with one-piece enclosure lid or SHP
75-10 with two-piece enclosure lid
1. Close the inverter ((see Section 5.12, page 32)).
2. Restore the DC power supply in the distribution
board (DC-Combiner).
3. Switch on the AC miniature circuit breaker of all
three line conductors.
4. Turn the DC load-break switch of the inverter to
position I.
STP 60-10 with two-piece enclosure lid
1. Close the inverter ((see Section 5.12, page 32)).
2. Turn the DC load-break switch of the inverter to
position I.
3. Restore the DC power supply in the distribution
board (DC-Combiner).
4. Switch on the AC miniature circuit breaker of all
three line conductors.
SHP75-10-STP60-10-IA-xx-20
6 Initial Setup and Start