APPLICATION
compli sewage lifting stations are LGA
certified and are suitable for lifting se-
wage from toilets and urinals, and do-
mestic wastewater containing the usual
impurities.
The tanks can withstand submersion to
a depth of not more than 2 m of water
and a submersion period of up to 7 days.
The control unit cannot withstand sub-
mersion, but is splash-proof in accord-
ance with IP 44.
If installed in compliance with the regu-
lations and used properly, then this con-
trol unit meets the protective require-
ments of the EMC Directive 2004/108/
EC and is suitable for domestic use and
connection to a power supply from the
grid. When connected to an industrial
mains within an industrial operation
with power supply provided by a com-
pany-own high-voltage transformer, in-
sufficient immunity to interference has
to be expected.
When using the pumps, the relevant na-
tional laws, regulations and stipulations
must be adhered to, for example:
• Sewage lifting stations for building
and ground drainage systems (e.g.
EN 12050 and EN 12056 in Europe)
• Installation of low voltage systems
(e.g. VDE 0100 in Germany)
• Safety and working materials (e.g.,
BetrSichV and BGR 500 in Germany)
• Safety in wastewater systems (e.g.,
GUV-V  C5, GUV-R  104 and GUV-
R 126 in Germany)
• Electrical systems and operating re-
sources (e.g., GUV-V A2 in Germany)
10
• Explosion protection EN 60079-
0:2009, EN 60079-1:2007, EN 60079-
14:2008, EN 60079-17:2007 and EN
1127-1:2007
Supply package
• One or two tanks with a DN 150 inlet
clamping flange
• Two submersible drainage pumps
• Duckfoot bend for the pumps
• Flexible connector(s) with clamps for
the DN 70 vent pipe
• Flexible connectors with clamps for
the duckfoot bend
• Flexible connector with clamps for
the pressure pipe
• Fastening materials for tank and
duckfoot bend
• Control unit
Operating mode: Intermittent opera-
tion S3; see "Technical data"
INSTALLATION
The pump must be installed so that it
is buoyancy-proof and free-standing. At
least 60 cm free working space must
be provided around and above the parts
that require access for operation or
maintenance.
Ventilation: The vent pipe must be vent-
ed above roof level.
Inlet: A wastewater stop valve must be
fitted in the tank inlet.
In order to continue using the pump
in the event of a fault or maintenance
work, a maintenance valve must be fit-
ted between each pump and the tank.
Pressure pipe: A further wastewater
sluice valve must be installed behind
the EN-certified swing-type check valve
in the pressure pipe. The pressure pipe
must be laid in a loop above the local
backup level.
A pump sump must be provided to fa-
cilitate the disposal of water from the
pump installation area.
compli 1500 and compli 2500 sewage
lifting stations are supplied as assem-
bly groups and are assembled on site by
a plumbing company.
ATTENTION! All screws and bolts that
are used for fixing individual compo-
nents to the tank should be tightened
with a torque of no more than 6 Nm.
Installing the tank
Close the sluice valve in the inlet (ac-
cessory) to prevent any leakage of water
during the installation work.
Screw the four angle brackets to the
sides of the tank. ATTENTION! En-
sure that the tank does not become
deformed due to overtightening the
screws, otherwise this could result in
leakage.
Slide the lifting station, together with
the clamping flange, as far as possible
onto the inlet pipe and then align them.
If a DN 150 side inlet is used, it must
first of all be opened up at the location
marked using a Ø 152 hole saw and
then deburred. The standard inlet must