The chapter "Safety instructions" must be heeded.
6.1 Setting up for operation
Before the separator is put into operation, please make
sure that:
•
the separator is clean and the interior is free from any
objects which may have been placed inside during ship-
ping or installation.
•
the separator is completely filled with clean cold water.
Completely filling the separator is complete when water
begins to drain from the outlet.
•
Lift the floater in the guide tube and check floating
position and movability. For light fluid separators:
Push coalescence insert in the designated guide.
6.2 Initial Instructions
Placing the separator into full operation is normally handled
by a licensed tradesman although upon request can be hand-
led by a KESSEL representative.
The following personnel should be on hand when the initi-
al instructions for placing the separator into operation are
given:
2020/09
Commissioning
•
Building facilities manager
•
Building maintenance workers
•
Contracted plumber / tradesman
•
Contracted disposal company
What to do:
•
C heck to make sure the separator is completely wa-
tertight. Check to make sure that during transport
and installation that no damage to the separator was
caused. Check to make sure all connections to the
separator (inlet, outlet, refill, rinse pipes etc.) are in per-
fect working order.
•
R epresentative should discuss all necessary informati-
on regarding the disposal.
•
R epresentative should take the customer step by step
through all stages of a separator disposal.
•
After the separator has been emptied (disposed) all
necessary paperwork and documentation should be
handed over to the customer.
•
T he separator should be returned to service by filling the
separator with fresh, cold water.
6.3 Commissioning report (see attachment)
The comissioning form is to be filled out complete and
signed by the customer´s representative and their client."