7 Commissioning the Inverter

7
Commissioning the Inverter
Requirements:
☐ The circuit breaker must be correctly rated.
☐ A means of disconnecting the inverter from the PV array must be present.
☐ The inverter must be correctly mounted and closed.
☐ All cables must be correctly connected to the terminals.
☐ Unused openings for the DC connection in the inverter enclosure must be closed with UL-listed
type 3R filler plugs.
☐ Unused openings for the Ethernet connection or the communication connection in the inverter
enclosure must be sealed tightly. The factory-mounted filler plugs can be used for that purpose.
Procedure:
1. Make sure that the AC cable is routed so that it cannot be damaged by the partition in the
lower enclosure lid.
2. Insert the lower enclosure lid from above and flip it
down. Make sure that the ribbon cable of the
communication assembly is not clamped and that
the screws must protrude from the lower enclosure
lid.
3. Tighten all six screws with an Allen key (AF 3) in the
order 1 to 6 (torque: 2.0 Nm (17.7 in-lb)). Make
sure that the ribbon cable of the communication
assembly is not clamped. By tightening the screws in
the prescribed order, you avoid warping the
enclosure lid, which would keep it from sealing
correctly. Tip: If the screws fall out of the lower
enclosure lid, insert the long screw into the lower
middle hole and the five short screws into the other
holes.
4. Switch on all DC disconnectors between the inverter and the PV array.
5. Switch on the circuit breaker and all AC disconnectors.
☑ The green LED is glowing. Feed-in operation begins.
✖ Green LED is flashing?
The DC input voltage is still too low.
• Once the DC input voltage is sufficiently high, feed-in operation begins.
✖ The red LED is glowing?
There is probably an error.
• Rectify the error (see Section 10 "Troubleshooting", page 45).
38
STPTL-US-10-IA-xx-22
SMA Solar Technology America LLC
Installation Manual