Commissioning; Commissioning Procedure; Commissioning The Inverter - SMA SUNNY BOY 3.0-US Instructions D'installation

Masquer les pouces Voir aussi pour SUNNY BOY 3.0-US:
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

SMA Solar Technology America LLC
7 Commissioning
7.1

Commissioning Procedure

This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure
1.
Commission the inverter.
2.
Establish a connection to the user interface of the inverter.
There are three connection options available to choose
from:
• Direct connection via WLAN
• Direct connection via Ethernet
• Connection via Ethernet in the local network
3.
Log into the user interface.
4.
Configure the inverter. Please note that the personal
SMA Grid Guard code for changing the grid-relevant pa-
rameters must be available after completion of the first ten
feed-in hours (see "Application for the SMA Grid Guard
code" available at www.SMA-Solar.com).
5.
Ensure that the country data set has been configured cor-
rectly.
6.
Make further inverter settings as needed.
7.2

Commissioning the Inverter

Requirements:
☐ The AC circuit breaker must be correctly rated and mounted.
☐ A means of disconnecting the inverter from the PV array must be present.
☐ The inverter must be correctly mounted.
☐ All conductors must be correctly connected.
☐ Unused enclosure openings must be sealed tightly with sealing plugs.
Installation Manual
7 Commissioning
See
see section 7.2, page 47
see section 7.3, page 49
see section 7.4, page 52
see section 7.5, page 53
Inverter user manual
Inverter user manual
SB30-77-1SP-US-40-IA-xx-13
47

Publicité

Table des Matières
loading

Table des Matières