INSTALLATION 
CONNECTION 
7.1 LOCATION 
 
Equipments  that  will  be  used  in  a  ATEX  zone  should  be 
certified accordingly and should fully comply with applicable 
regulations. 
 
The choice of the pump location should permit a proper cooling of the 
motor and should respect following limits : 
 
Location  will  be  chosen  to  ensure  space  reservation  for  maintenance 
and inspection. 
Check that there is ample overhead for lifting and that lifting devices are 
available. 
7.1.1
FOUNDATION 
Pump set can be installed on various types of foundations (on a concrete 
ground, on a foundation concrete block, on a steel framework, ...). It is 
the  responsibility  of  the  end  user  to  select  proper  pump  foundation 
type. Noise level and vibrations transmitted by the machine depend on 
the quality of foundation. 
Following rules are general instructions that should be respected : 
‐  Base  frame  or  pump  matting  plate  should  be  fastened  to  a  rigid 
foundation with no risk of distortion while the pump is running. 
‐  Make  sure  that  the  foundation  concrete  is  of  sufficient  strength  (min 
quality X0 to DIN 1045). Generally, the weight of foundation is around 3 
times  the  pumpset  weight.  With  pump  set  dimensions  and  concrete 
density  it  is  then  possible  to  calculate  the  dimensions  of  the  required 
foundation block. 
‐  Surface  under  pumpset  should  be  flat  and  should  not  create  any 
distortion of base  plate after tightening of foundations bolts. If surface 
quality  is  not  sufficient,  add  shims  between  ground  and  base  plate. 
Distortion on base plate surface should be limited to 0,4mm/m after the 
baseplate is definitively fastened to foundations. 
Coupling alignment is checked before shipment (pumps and 
 
motor deliver ed on a common baseplate) If coupling is not 
correctly aligned after installation works are done this indicates that the 
baseplate  has  become  twisted  and  leveling  should  be  corrected  by  re‐
shimming. 
Even  if  foundation  works  have  been  done  with  care,  it  is  necessary  to 
check  coupling  alignment  after  the  baseplate  is  definitively  secured  to 
the foundation. 
7.1.2
ANCHORING 
Chemical anchoring device should be preferred to fasten a baseplate on 
an existing foundation. 
Anchor bolts can be used if foundation block is to be built. 
1 – Anchor bolt 
2 – Baseplate 
3 – Concrete foundation block 
 
Folded steel fabricated baseframes will be grouted to insure its rigidity. 
All manuals and user guides at all-guides.com
AND 
ELECTRICAL 
 
 
 
Using of shrink free grout is the most efficient. Grouting ensures correct 
positioning of the baseframe and reduces vibrations transmission to civil 
work.  Foundation  work  surface  preparation  and  leveling  of  baseframe 
will  be  performed  in  the  state  of  the  art  and  should  be  done  before 
grouting of the baseplate. 
 
Foundation  bolts  should  be  fully  tightened  only  after  the 
 
grout has cured. 
 
Installation without foundation : 
1 – Intermediate plate 
2 – Nut 
3 – Leveling element 
4 – Foot base 
5 – Washer 
6 – Fastening nut 
7 – Washer 
8 – Baseplate fastening screw 
 
7.1.3
POSITIONING 
Pump  baseplate  (cast  iron  base  plate  or  fabricated  steel  baseframe) 
should  be  installed  horizontally  to  ensure  bearings  lifetime  and  proper 
flow of pumped fluid. 
7.1.4
COUPLING ALIGNMENT  
Pumpsets  assembled  with  a  flexible coupling  must  be  aligned  after  the 
baseframe  has  been  definitively  fastened  to  the  foundation.  Use  low 
thickness shims (0,2 to 1 mm) to modify coupling alignment. Adjust the 
motor height first. Sometimes it is necessary to add shims under pump 
feet too. 
 
Aligment  of  coupling  should  be  performed  with  particular  care 
when  the  pumpset  is  installed  in  an  hazardous  area.  Correct 
alignment  will  avoid  abnormal  increasing  of  the  pump  and  motor  ball 
bearings temperature.  
 
Thermal expansion : the pump and motor will normally have to be 
aligned  at  ambient  temperature  with  an  allowance  for  thermal 
expansion at operating temperature. In pump installation involving high 
liquid temperatures, alignment should be checked again when operating 
temperature is reached (pump and piping). Alignment quality should be 
checked just after machine shut down. 
 
 Pump  and  driver  must  be  isolated  electrically  before  alignment 
operations are performed. 
 
Pump and motor were aligned before dispatch. If it is necessary to 
use  very  thick  shims  to  adjust  coupling  alignment  on  site  this 
means that the baseplate is twisted. Leveling has to be modified. 
 
Checking the coupling alignment : 
Check distance between the two half couplings. 
Check radial and axial deviation. 
Several types  of flexible couplings can be used. Refer to coupling 
operating  instructions  to  know  adjustment  values  and 
misalignment limits. 
 
Several  methods  can  be  used  to  make  coupling  alignment.  Choice  of  a 
method  will  depend  on  the  type  of  equipments  available  on  site.  Two 
operating methods are briefly described hereafter. They can be used if 
basic metrology equipments are available : 
11 