RESERVED TO THE INSTALLER
CHECK TO BE CARRIED OUT WHEN THE INSTALLATION IS COMPLETE
1
CHECK OF SCREW SECURING LIFT TO FLOOR CORRECT INSTALLATION AND SEALING CAPACITY
2
CHECK OF CORRECT ELECTRIC HOOK-UP (ACCORDING TO STANDARDS)
3
CHECK OF CORRECT PNEUMATIC SUPPLY (IF AVAILABLE
4
CHECK OF CORRECT OPERATION (ACCORDING TO MANUAL)
5
CHECK OF THE ELECTRIC SAFETY DEVICE CORRECT OPERATION
6
CHECK OF EMERGENCY SWITCH / DISCONNECTOR
7
CHECK OF MECHANICAL SAFETY DEVICES CORRECT ENGAGEMENT
8
CHECK OF ARM-LOCK CORRECT ENGAGEMENT
9
CHECK OF FOOT GUARDS CORRECT ASSEMBLY
10
CHECK OF HYDRAULIC SYSTEM PERFECT SEALING
11
CHECK OF OIL LEVEL
12
CHECK OF EMERGENCY LOWERING OPERATION
13
CHECK OF LABEL APPLICATION ACCORDING TO DIAGRAM
14
CHECK CORRECT LUBRICATION OF THE SLIDIN AREAS
15
FULL-LOAD LIFT TESTING
16
CHECK FOR DOCUMENTS (instruction manual, Declaration of Conformity and Inspection records)
17
TRAINING OF THE PERSONNEL AUTHORIZED TO USE THE LIFT
18
INSPECTION RECORDS FILLING OUT
NOTE
Date
Client : Cachet et signature
PE 2009
l'installateur : Cachet et signature
YES
NO
NOTES