Minimum Clearances; Requirements For The Installation Site - Vaillant VPV I 3000/1 400V Notice D'emploi

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

4 Installing the inverter
4.4

Minimum clearances

B
A
200 mm
B
60 mm
24
B
Minimum clearance
B + 95
4.5

Requirements for the installation site

Ensure that the minimum clearances (→ Page 24) are
complied with.
Ensure that the direct current cabling can be routed from
the photovoltaic modules to the inverter.
Ensure that the alternating current cabling can be routed
to the meter cabinet.
Ensure that the installation site is fixed, vertical and level.
Ensure that the immediate surroundings of the installa-
tion are difficult to ignite.
Ensure that the installation site is free from continuous
vibrations.
Ensure that the installation site is located in an air-condi-
tioned or non-air-conditioned interior room.
Ensure that the installation site complies with the re-
quirements of climate class 3K3 in accordance with
IEC 60721-3-3.
To use the web portal, ensure that an Internet router is
available.
If required, ensure that the data connections for con-
necting other approved products can be routed to the
inverter.
Installation and maintenance instructions VPV I 0020273404_00
B + 95