8.3 Fill and vent the hydraulic systems
The lift is factory pre-installed; meaning the hoses and
pipe connections are properly assigned.
Finally, check the power connection, check for correct hy-
draulic oil in the proper volume and leak-tightness of the
connection when setting up the lift.
If the hose connections are still open, e.g. for the purposes
of hose extension, then air may be entrapped resulting in
start up problems or challenges with smooth running.
Check and ensure proper allocation of hose connections.
This procedure must always be completely
!
carried out. This means, first fill and then
vent.
Correct method of filling and balancing (lift
with HyperFlow system):
• Close the emergency discharge screws „N1" (14) and
„N2" (15).
• Push the
o
„Lift" button to move the lift upwards without
a load to the maximum height.
• Continue holding the
o
„Overflow procedure". Oil flows from the hydraulic
pump through the command and downstream cylinders
and back into the tank.
• After releasing the
o
„Lift" button, the lift lowers a few
millimetres and closes the overflow openings.
• The system is now vented and smooth operation can
happen.
• The lift now has its normal operating function.
8.4 Commissioning
i
Before commissioning, a single safety inspection must
be done (use the "single safety inspection" form).
If the lift set up is done by a specialist (factory trained as-
sembler) then he can also do the safety inspection. If the
set up is done by the operating company then a specialist
must be tasked with the safety inspection. The specialist
confirms seamless operation of the lift on the set up proto-
col for single safety inspection and releases the lift for use.
After commissioning, the set up protocol must be com-
i
pleted and sent to the manufacturer.
8.5 Changing the assembly location
To change the assembly location the pre-conditions must
be met according to the assembly guidelines. The loca-
tion change is to be done according to the following se-
quence.
• Move
the
lifting
stage
1,000 mm.
• Loosen and remove all hose covers.
• Loosen base plate anchors.
• Lower the lift to the lowest position.
• Disconnect power.
OPI_JUMBO LIFT 4000 NT_V4.1_DE-EN-FR-ES-IT
„Lift" button. This starts the
upwards
to
approx.
• If necessary, disconnect the hydraulic lines on the operat-
ing unit only, and seal them off with blind stoppers.
• If necessary, suction off the hydraulic oil.
• Transport the lift with the unit to the new set up location.
• Assemble the lift according to the procedure during as-
sembly and anchoring before first commissioning.
Use new anchors. The old anchors
are no longer fit for purpose!
i
Before re-commissioning, a safety inspection must be
done by a specialist (use the regular safety inspection
form)
8.6 Selecting the anchors
Anchor
Without floor
type
cover
(screed/tiles)
Heavy duty anchor
Liebig/
BM 10-15/70/40
Strongtie
Fischer
FH 15/50 B
Hilti
HSL-3-G M10/40
Injection anchor
MKT
VMZ-A 75 M12-
25/145
Hilti
HIT-HY 200 with
HIT-Z M12
Fischer
Highbond FHB II-A S
M12x75/25
i
Similar value anchors and other known brands of
anchor manufacturers can be used when considering
the conditions.
With floor
covering
(screed/tiles)
Anchor length
depends on the
floor covering
Anchor length
depends on the
floor covering
73