ELECTRICAL INSTALLATION
The equipment is installed in the electrical housing.
1 - After inserting the actuator, make the connections by following the operations indicated in the ECA8 control unit (Fig. 1).
2 - Select short routes for the connections with multicore cable of the type prescribed by current standards.
3 - The gate's earthing device must conform to current standards.
The manufacturer accepts no liability for damage arising from negligence in this respect.
4 - In accordance with European safety standards, it is recommended that a mains two-pole switch is installed in order to be able to di-
sconnect the power supply before carrying out maintenance on the gate and to disconnect the terminal of the card power supplies.
5 - Check that each individual device (photocells, key selector, etc.) works effectively and efficiently.
6 - Apply adequate supplementary safety measures to the automatic system where required.
Fitting/replacing the card
In case of REPLACEMENT, it is necessary to:
- IMPORTANT! Switch off the power supply.
- Disconnect all connections.
- Remove the card by undoing the fixing screws.
- Position the new card and fix in place.
- Restore the connections.
- Restore the power supply, reprogram and save the radio controls.
Electrical connections and hook-up to the mains supply
The N.C. contacts must be jumpered to earth (GND terminal) when not used. Otherwise the automatic gate system will NOT function!
If a N.O. input is closed, or a N.C. input is open, the PROG-DL8 LED flashes at high frequency.
PLUGIN CARDS - CONFIGURATION
EC 80 can operate on its own or with the insertion of a plugin card (purchased separately).
Connector CN2 (SLOT 1) can accommodate the following plugin card:
- art. ECFC (Limit switch control - optional)
The ECFC card must be connected to the open and closed position limit switches of the gate leaves.
During the travel path learning procedure, the type of the limit switch contacts is also memorised, which is either Normally Open (N.O.) or
Normally Closed (N.C.).
Limit switches of different type can be used for the two gate leaves.
START-UP
Before starting up the system for the first time, make sure that no-one is in the vicinity of the automatic gate.
After completing and checking the electrical connections, power up the equipment and immediately execute TRAVEL PATH LEARNING (see
Programming paragraph).
GENERAL FEATURES