OPERATION

20.1. RECOMMANDATIONS
 Open the general water tap, if it is closed, then open the water shutoff valve dedicated to
the machine.
 Do not put the supplying voltage at this moment.
 Verify the presence of water, by reading the pressure of the mains water inlet on the M2
manometer pump.
20.2. INITIAL FILLING
 Ensure that steam taps operating levers 'V' are open (up).
 Put the ON/OFF switch 'C' to position 1 (power on).
 The key board turn on.
 The boiler fills automatically, without heating.
 The machine start to heat automatically, only when the level probe is reached by the water
 A scrolling LED on keypads can inform the user about the status.
 Close the steam tap "V" and wait.
 When the scrolling leds stops : The machine is ready to operate
20.3.
Further fillings will run automatically, according to the hot water needs.
The water level in the boiler is controlled by the electronics, by the means of a level
probe.
SACOME, CONFIDENTIAL Document,
FURTHER FILLINGS
Edition 07/2018 - CC100
TECHNICAL DOCUMENTS - page 33
it is forbidden to duplicate or communicate this document without previous authorization.