OPEN SET: 4 lifting points
NOTE
It is mandatory to use all four lifting
points (2) set up on the base on the
control side and on the opposite side.
The main lifting hook must be used
together with a rocker arm ( like when
lifting "
SOUNDPROOF with EFT" identified
with the number (1))
lifting chains at a distance to prevent
them from coming into contact with
the generator. Adjust the length of the
lifting chains in order to balance the
load
and
to
minimise
between them (chains as vertical as
possible).
, which keeps the
the
angle
SOUNDPROOF: 1 lifting point
NOTE
It is mandatory to use the preset
lifting points (2) on the roof. The
lifting hook must be positioned as
close as possible to the vertical of
the generator's lifting ring to keep it
from swaying when lifted.
SOUNDPROOF: 2 lifting points
4.INSTALLATION
GSW