Plug the mains plug of the control unit into the socket. The plant
will initialise automatically.
Note: The mains power supply cable must be equipped with a
fault current circuit breaker.
During the first initialisation of the plant, the control unit re-
quests four basic settings. The control unit display shows a
query for
1. the language for the user prompting
2. the date and the time
3. the desired purification class C or D
4. the required nominal size of the plant.
By pressing the movement keys / direction keys, the desired
setting can be highlighted with a marking bar. Pressing the
enter key stores the selected setting in the system memory. As
soon as the 4 presettings have been made, the control unit
loads the program memory and automatically enters into ope-
rating mode.
The plant is now ready for operation.
5.2 Operator's duties
Checking
- for transport or installation damage
- for structural defects
- all electrical and mechanical components for seat and func-
tion
- floater function
- hose connections
- line connections
- syphons (see point 8)
- aerator
5. Commissioning
5.3. Instruction of the customer based on the installation
- Perusing the installation and operating instructions with the
customer
- Operating the plant (explaining and describing)
- Explaining the operator duties to the customer (disposal,
maintenance, operation of a small biological sewage treat-
ment plant, operations diary)
109
instructions