Starting the
charge accept-
ance test manual-
ly
Retrieving param-
By pressing the info button, the parameters are displayed in the following sequence:
eters during the
-
charge accept-
-
ance test
-
-
-
Charge accept-
The battery is OK, when the charger will switch automatically to standard charging mode
ance test finished
and charge the battery after the charge acceptance test has been carried out.
- battery OK
By pressing the Info button stored test parameters and the actual charging parameters can
be viewed:
64
Charger detects that the battery is connected, carries out a self-test and starts the
charge acceptance test.
Self test
CAUTION! Risk of serious damage if the charging terminals are connected incor-
rectly. The reverse polarity protection facility is inoperative if the current input test
is started manually (battery voltage < 1.5 V).
Connect charging terminals to correct poles and ensure proper electrical connec-
tion to vehicle terminals.
Connect (+) charging terminal to positive pole on battery
1
Connect (-) charging terminal to negative pole on the battery, or to vehicle body (e.g.
2
engine block) in the case of vehicle electrical systems.
Press start/stop button for approx. 5 secs
3
A query regarding correct polarity of the charging terminals is displayed:
Starting the charge acceptance test confirms the correct polarity connection. If the-
charge acceptance test is not started within 2.5 secs, the device reverts to menu
mode.
Ensure charging terminals are connected to correct poles
4
Start the charge acceptance test by pressing the start/stop button
5
The charger starts the charge acceptance test.
actual battery current
actual battery voltage
amount of charge (Ah) fed in so far
energy (Wh) fed in so far
time that has elapsed since the start of the test
Charge acceptance test