INDOOR VENTING — General Requirements
If you are considering connecting this heater to a pre-existing vent system, make sure that the vent system meets the
appropriate venting requirements as given in this manual on pages 15-20. If not, replace the vent system. DO NOT use a
draft hood with this heater. The MasterTemp heaters are capable of a 270-degree discharge rotation and with a vent gas
temperature less than 204° C (400° F). The total length of the horizontal run must not exceed the length that is listed in
Table 5
on
page
17.
HEATER CLEARANCES — General Requirements
INDOOR INSTALLATION AND OUTDOOR SHELTER
The following clearances must be maintained from the nearest walls: (See Figure 19, 20 & 21)
TOP ................................... 15 cm (6 in)
EXHAUST SIDE ............... 15 cm (6 in.)
Note (*) For service access it is advisable to allow for sufficient clearance on at least one door panel. The heater is
designed for installation on combustible flooring. For installation on carpeting, the heater must be mounted on a metal or
wood panel that extends at least 10 cm (4 in) beyond the base of the heater. Note: Wall sensitive to heat
(for example wood), must be protected by a suitable insulation. If the heater is installed in a closet or alcove, the entire
floor shall be covered by the panel. On an outdoor shelter installation, the exhaust discharges into a vent pipe. Orient the
heater so that the vent pipe does not interfere with adjustment of the operating controls. The control panel located on the
top panel can be rotated to any of the three sides of the heater for easy access. However, the control panel must not be
located on the side where the vent is located.
(*) For service access, it is advisable to allow for
sufficient clearance on at least one door panel.
15 cm*
(6 in)
Figure 19.
OUTSIDE VENT COVER REMOVAL
THE HEATER IS SUPPLIED FROM THE FACTORY WITH A BUILT-IN STACKLESS OUTSIDE VENT FOR OUTDOOR INSTALLA-
TION. REMOVE THE OUTSIDE VENT COVER FOR OUTDOOR SHELTER INSTALLATION.
COMBUSTION AIR SUPPLY
For indoor installation, the heater location must provide sufficient air supply for proper combustion and ventilation of the
surrounding are in accordance with European Standard Codes of Practice. The minimum requirements for the air supply
specify that the room in which a heater is installed should be provided with two permanent air supply openings; one
within 30 cm (12 in) of the ceiling, the other within 30 cm (12in) of the floor for combustion air, in accordance with the
European Standard Codes of Practice as applicable, and any local codes that may apply. These openings shall directly, or
through duct, connect to outdoor air.
Pentair Water Pool and Spa, Inc. does not recommend indoor installations that do not provide combustion
air from outside the building. (Continue on next page)
P/N 475106 Rev. D 1/2016
All manuals and user guides at all-guides.com
HEADER SIDE ........................... 15 cm (6 in.)
DOOR PANELS* .......................... 15 cm (6 in.)
15 cm
*
(6 in)
15 cm
*
(6 in)
15 cm *
(6 in)
Figure 20.
MASTERTEMP
Section 2. Installation
Chimney or Gas Vent
Vent Cap and
Riser Furnished
by Installer
15 cm
(6 in)
Side
Heater
Wall Vent
Pool and Spa Heater Installation and User's Guide
| 15
Outlet Air
Opening
Inlet Air
Opening

Publicité

loading

Ce manuel est également adapté pour:

Mastertemp mt300hdMastertemp mt400hd