4
Installation
Transport information
The tank must be carried by the two recessed handles.
The handles on the cover are not to be used to carry the
tank!
4.1
Setting the system in place
Make sure there is enough space for maintenance work to be carried out in accordance with the relevant directives and
standards (EN 12056-4 and EN 12050-1). We recommend at least 60 cm working space all round the plant.
If provided, lay out the sound insulating underlay mat so that the system can be positioned on it.
The system's control unit must be positioned in such a way as to prevent any unauthorised use.
Consequential damage can occur in the building if the system is switched off accidentally.
Pre-conditions:
The system must be installed on a level surface that is sufficiently load-bearing (take into account weight when filled =
tank volume in kg plus 70 to 250 kg, depending on system design).
The surface must be suitable for holding the floor fixings (per screw, 0.9 kN), which are intended to prevent the system in
the pump sump from floating up.
Connection pipes (inlet and outlet as well as venting) must be fixed so that they are self-supporting, they must not exert
any load on the system.
32 / 140
016-228_01