Higher Voltage : Y Connection; Y /  Starter; Use Of A Frequency Inverter; Start-Up - Samson NESE Manuel D'installation Et Mise En Service

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

 
 
7.3.3
HIGHER VOLTAGE : Y CONNECTION 
Voltage : U3 
 
 
7.3.4
Y /  STARTER : 
 
Grounding  of  the  complete  pumpset  will  be  performed  with 
 
special  care.  Earthing  will  avoid  any  electrostatic  accumulation  in 
components  of  the  pumpset.  Each  part  of  the  pumpset  should  be 
connected  to  earth  with  a  correctly  calibrated  bonding  strap  or  cable 
(motor winding, motor frame, coupling guard, pump baseframe). 
 
7.4 USE OF A FREQUENCY INVERTER 
When  pump  is  used  with  a  variable  speed  drive,  make  sure  that 
 
the  frequency  inverter  instructions  and  operating  manual  is 
available and known. 
 
The  electric  motor  that  is  supplied  with  the  pump  may  be  connected 
under  conditions  to  a  VSD.  Variable  speed  will  be  used  to  reach  pump 
required duty point on site. To ensure a reliable use of the equipment a 
few precautions should be taken : 
 
Electrical requirements : 
  Variable  frequency  drive  will  not  generate  voltage  peak  higher  than 
850V  (motor phases isolation) and dU/dt values higher than 2500 V/µs 
(winding  isolation).  If  those  values  can  be  reached,  a  filter  should  be 
installed  :  ask  inverter  manufacturer  for  proper  selection  and  motor 
manufacturer for limit values. 
  Choose  a  vector  control  inverter  or  use  a  quadratic  V/F  control 
inverter. 
 Check that motor nominal voltage is never exceeded. 
Power supply cable should comply to ATEX regulation. Ensure that 
 
motor winding is equipped with CTP temperature sensors inside. 
A  physical  barrier  should  separate  power  supply  cables  and  low 
 
voltage cables to avoid analog signal distortion. 
 
Hydraulic requirements : 
 A dedicated suction pipe should be dedicated to each pump used with 
a negative suction head (suction lift). 
  Check  that  the  pump  NPSH
  at  minimum  speed  is  always  lower  than 
R
system NPSH
 . 
A
 
Mechanical requirements : 
  Lower  speed  should  not  fall  under  40%  of  pump  nominal  speed  to 
avoid any vibrations and an unstable flow. 
The  harmonic  currents  that  are  created  by  the  VSD  pass  through 
 
motor  ball  bearings.  Standard  ball  bearings  can  be  used  up  to 
55KW. For higher installed power (see engraved power on motor name 
plate),  the  motor  should  be  equipped  with  isolated  ball  bearings 
(specific ball bearing) or with isolated bearing housing (and standard ball 
bearing). 
 
13 
 
8
START‐UP 
8.1 PRE‐COMMISSIONING 
If  the  pump  is  installed  in  a  potentially  explosive  atmosphere  or 
when dangerous or polluting fluids are pumped, it is advised (Zone 
2) or requested (zone 1) to install additional protection devices.  
Check following points : 
 Pump flow is always higher than authorized continuous minimum flow, 
 Pump never runs dry, 
 Normal leakage of the shaft seal is controlled, 
  Surface  temperature  bearings  housings  is  lower  than  the  maximum 
admissible surface temperature in selected ATEX zone, 
 Pressure on discharge side of the pump is lower than pump maximum 
allowable working pressure. 
 Set alarm and stop trips of sensors. 
 
In every cases check : 
 Quality of electrical connections, 
 Protection devices are installed, 
 Auxiliary piping are connected, 
 Flanges connections, 
 Suction line and pump casing are filled with fluid, 
 Motor direction of rotation is correct, 
 Coupling alignment is correct, 
 Oil level was checked and greasing of ball bearings has been done, 
 Coupling guard is installed. 
 
8.2 FILLING / VENTING 
Before the very first start‐up, pump casing and suction line must be filled 
with fluid (depending on piping system a vacuum pump may have to be 
used).  
Pump  casing  should  be  perfectly  vented  to  avoid  that  the 
mechanical seal runs dry.  
Take  precautionary  measures  when  manipulating  dangerous,  hot 
or  polluting  fluids.  Wearing  individual  protective  devices  is 
necessary. The operator must know the potential hazards. 
 
The mechanical seal housing should be completely vented. A vent valve 
is located on the top of the bearing bracket. 
Burn  hazard  when  manipulating  the  pump.  Vent  valve  or  vent 
screw  should  be  opened  slowly  and  left  open  until  pump  is 
completely  vented.  Then  close  venting  device.  Use  of  protections  and 
pincers is necessary. 
Complete venting may take a long time. An incomplete venting of 
pump could drive to a rapid destruction of the mechanical seal and 
the internal shaft bearing. 
 
 
8.3 START‐UP 
If  a  barrier  fluid,  flushing  fluid,  cooling  fluid  or  a  heating  fluid  is 
used,  check  that  auxiliary  systems  are  activated  and  working 
correctly before pump start‐up. 
 
 Close isolating valve on pump discharge side. 
 Open all valves in suction line. 
  Proceed  to  pump  priming  (if  not  already  done).  Pump  casing  and 
suction pipe should be completely filled with fluid. 
  ENGLISH  
 
 

Publicité

Chapitres

Table des Matières
loading

Table des Matières