The switch box should be installed in the control room. It can
be fixed there in any place you wish. See the drawing in
section 10 for fastening dimensions.
5.1.2

Space requirements

Leave enough space to remove the lid and easily access the
plugs. See the dimensional drawing in section 10.
5.1.3

Fastening elements

Fix the switch box with screws.
5.2

Electrical connection (Qualified specialist)

WARNING
Risk of electric shock due to incorrect connections!
Electrical connections must always be carried out by
authorised specialists.
Observe VDE and utility company regulations.
Install a disconnecting device with at least a 3 mm contact
gap per pole to interrupt the power supply.
Protect power supply with a ground fault circuit interrupter,
nominal residual current I
Only use suitable cable types. Observe functional integrity
class E90 or higher.
Adjust minimum diameter of the electrical pipes to
accommodate the motor output and pipe length.
Do not bend or squash the pipes.
If hazardous situations can occur, provide an emergency off
switch according to DIN EN 809. The builder/operator must
make a decision according to this standard.
09|2019
≤ 30 mA.
FN