Epson V12H949001 Instructions D'installation page 25

Tableau blanc tout-en-un epson/support pour brightlink pro
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

Installation Instructions
APPENDIX
FASTENER INSTALLATION METHODS
NOTE:
Refer to Table 1 for appropriate hardware and pilot hole
sizes for various wall types.
Steel Stud / Drywall
1.
Hold metal channel on anchor (B1) flat alongside plastic
straps and slide channel through hole. (See Figure 62)
Drywall
Plastic straps
(B1)
Figure 62
2.
Holding plastic straps on anchor (B1), pull anchor away from
wall until channel rests flush behind wall making sure anchor
channel is positioned vertically on drywall, or steel stud (if
present). (See Figure 63)
3.
Slide plastic cap on anchor (B1) towards wall until flange of
cap is flush with wall. (See Figure 63)
Steel stud
(if present)
Drywall
Plastic cap
(B1)
Anchor metal channel
(side view)
Figure 63
4.
Snap off plastic straps on anchor at wall by pushing side to
side, snapping off straps level with flange of plastic cap.
(See Figure 64)
1
2
3
Steel stud
(if present)
4
Plastic straps
Anchor metal channel
(side view)
Figure 64
5.
Line up anchor with attachment point.
6.
Insert 1/4-20 x 1-3/4" Phillips pan head screw (B2) through
1/4" washer (B3), corresponding mounting hole in product
and into anchor (B1), and tighten until flush against product.
DO NOT over tighten! (See Figure 65)
Steel stud
(if present)
Drywall
(B3) x 4
6
(B2) x 4
Product
Anchor metal channel
(side view)
Figure 65
Wood Stud
NOTE:
Refer to Table 1 for appropriate hardware and pilot hole
sizes for various wall types.
1.
Use one 5/16 x 2-1/2" lag bolt (A1) through product and into
pilot hole. (See Figure 66)
2.
Repeat for remaining pilot hole.
1
(A1) x 2
2
Figure 66
V12H949001 / AN3WA100
Drywall
Plastic cap
25

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

An3wa100

Table des Matières