7 - TESTING AND COMMISSIONING THE AUTOMATION SYSTEM
The system must be tested by a qualified technician who must carry out
the tests required by the applicable standard according to the existing
risks, ensuring compliance with the standard provisions, in particular the
7.1 - Testing
All system components must be tested following the procedures descri-
bed in their respective operator's manuals;
ensure that the recommendations in Chapter 1 - Safety Warnings - have
been complied with;
Check that the bar can move freely once the automation system is re-
leased and that it remains stationary and balanced if left at a 45° angle
Check the correct operation of all the connected devices (photocells,
7.2 - Commissioning
Once all (and not just some) of the system devices have passed the
testing procedure, the system can be commissioned;
The system's technical dossier must be produced and kept for 10 years.
It must contain the electrical wiring diagram, a drawing or photograph of
the system, the analysis of the risks and the solutions adopted to deal
with them, the manufacturer's declaration of conformity for all connected
devices, the operator's manual for every device and the system main-
tenance plan;
Fix to the barrier lift body a data plate indicating the automation data, the
name of the person in charge of commissioning, the serial number and
the year of construction, and the CE mark
Also fit a sign specifying the procedure for releasing the system by hand;
Draw up the declaration of conformity, the instructions and precautions
24
EN 12453 standard which specifies the test methods to be applied to the
motorized doors
sensitive edges, emergency buttons, others) by carrying out barrier
opening, closing and stopping tests via the connected control devices
(transmitters, buttons, selector switches)
Perform the impact measurements as required by the EN 12453 stan-
dard, adjusting the control unit's speed, motor force and deceleration
functions if the measurements do not give the required results, until the
correct setting is obtained.
for use for the end user and the system maintenance plan and consign
them to the end user;
Ensure that the user has fully understood how to operate the system in
automatic, manual and emergency modes;
The end user must also be informed in writing about any risks and ha-
zards still present.