6 Commissioning
6.2.3 Bleeding the cable assembly
Proper cooling is ensured only if the entire cooling system has been bled. The cable assembly must bled at
the time of initial commissioning and every time the device is fully bled.
Connect the cable assembly's coolant hoses to the device, ensuring that the cooling circuit is closed.
1
Remove the coolant tank cap and keep the coolant tank open until the bleeding process is complete.
2
Remove the coolant return hose from the red-colored quick coupling and hold it over the coolant tank's
3
opening.
Switch on the device.
4
Seal the coolant hose or kink it and then open it abruptly. Repeat this process until coolant flows
5
continuously and without bubbles.
Switch off the device.
6
Connect the coolant return hose to the red-colored quick coupling.
7
Check the coolant level and fill as needed.
8
Seal the coolant tank.
9
6.2.4 Commissioning the flow control
A flow control is integrated as standard in the device, however, it must be connected via the supplied flow
control line. The available connection is suitable only for two-step operation. If a flow control is used,
the device switches off the welding current if the coolant level is low and the torch button is pressed. The flow
control is pre-set to 0.6–0.8 l/min.
13.1 Connecting diagram for flow control on page EN-22
EN - 14
ABICOOLER 1300 115V CSA
Open the device connection housing.
1
Disassemble one button line.
2
Disassemble the cap from the connection housing.
3