Installation

4.1
Choose suitable installation location
Pre-requisites for the operation of separator systems:
Ensure aeration and/or ventilation of the room.
Set-up area level and capable of bearing sufficient load (see "Technical data", page 19 ).
Room temperature at least 15 °C.
Sealed floor covering with integrated drain.
Hot and cold water connections available.
Room height at least 60 cm higher than the grease separator, so that the service access covers can be opened during
cleaning work.
At least 1 m free working space in front of the grease separator.
Inlet with calming section of at least 1 m (gradient 1: 50). Transition of on-site downpipe to calming section equipped with
2 x 45° bends.
If the inlet pipe is longer than 10 m horizontally, it must be vented separately.
4.2
Installing the pipes
Connect the inlet and outlet
Connection of inlet and outlet to the draining system on
site.
If the connections are to be mutually swapped, remove
them together with the screws (1) and seals (2) and
swap them accordingly. Make sure that the seals (3)
have been sufficiently lubricated.
Attachment of the refill inlet
Pull clips off the attachment clamp.
Pull the refill inlet pipe out of the attachment clamp.
Insert the refill inlet pipe with pre-assembled seal into the
opening for pipe penetration.
Slide in the refill inlet pipe in such a way that it can be
fixed in place with the attachment clamp.
Attach clips to the attachment clamp.
✓ Refill inlet is ready for operation.
The supply pipe to the refill inlet must be routed in such a
way that dormant lines are avoided. The risk of contami-
nating the lines with legionella should be excluded as far
as possible.