8.5 Start-up

Before start-up, the pump must be filled with
1.2 to 1.5 gallons of water to enable it to self-
prime, see fig. 14. The pump is self-priming
with a maximum suction lift of 25 ft.
Fig. 14 Priming the pump
When started, the pump begins to self-prime.
When it has been primed, the pump will auto-
matically change over to normal operation.
If the priming has not been completed within
5 minutes, the pump will stop automatically
and attempt to restart after 30 minutes. It is
possible to reset the pump manually, see point
2 in the table of section 9.1 Control panel.