Connection To The Mains Network; Cleaning Preserving Agent When Starting-Up Of Operation Initially; Ventilate Unit (Hydraulic System) If The Sound Of Inlet Valve Is Not Audible; Taking The Unit Into Operation With Coating Material - WAGNER Super Finish 23i Mode D'emploi

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

Super Finish 23i
4.4

CONNECTION TO THE MAINS NETWORK

Connection must always be carried out via
an appropriately grounded safety outlet with
residual-current-operated circuit-breaker.
Before connecting the unit to the mains supply, ensure that
the line voltage matches that specified on the unit's rating
plate.
4.5
CLEANING PRESERVING AGENT WHEN
STARTING-UP OF OPERATION INITIALLY
1. Open the discharge tap (5).
2. Fill up hopper with a suitable cleaning agent.
3. Set ON/OFF switch (1) to ON; the unit commences to run.
4. Turn the pressure regulating knob (2) to the right until
the stop is reached.
5. Wait until cleaning agent is emitted from the return hose.
6. Turn the pressure regulating knob (2) back approx. one
rotation.
7. Close the discharge tap (5).
Pressure is rising up inside the high pressure hose (visible
at pressure gauge (3))
8. Point the gun into an open collecting container and pull
the trigger guard at the gun.
9. The pressure is increased by turning the pressure regulat-
ing knob (2) to the right. Set approx. 10 MPa (100 bar) at
the pressure gauge.
10. Pump the cleaning agent out of the unit for approx.
1 - 2 min. (~5 litres) into the open collecting container.
4.6
VENTILATE UNIT (HYDRAULIC SYSTEM) IF THE
SOUND OF INLET VALVE IS NOT AUDIBLE
1. Set ON/OFF switch (1) to ON.
2. Turn pressure regulating knob (2) three revolutions to
the left.
3. The hydraulic system is ventilated. Leave the unit on for
two to three minutes.
4. Then turn pressure regulating knob (2) to the right until
stop.
5. Press inlet valve pusher (4).
Sound of the inlet valve is audible.
6. If not, repeat points 2 and 4
5
4
4.7
TAKING THE UNIT INTO OPERATION WITH
COATING MATERIAL
1. Open the discharge tap (5).
2. Fill coating material into the hopper.
3. Press inlet valve pusher (4) several times to release pos-
sibly clogged inlet valve
4. Set ON/OFF switch (1) to ON; the unit will start.
5. Turn the pressure regulating knob (2) to the right until
the stop is reached.
When the noise of the valves changes, the unit is bled and
takes in coating material.
6. If coating material exits from the return hose, turn the
pressure regulating knob (2) back approx. 1 rotation.
7. Close the discharge tap (5).
Pressure is rising up inside the high pressure hose (visible
at pressure gauge (3)).
8. Pull the trigger of the gun and spray into an open collect-
ing container in order to remove the remaining cleaning
agent from the unit. When coating materials exits, release
the trigger.
9. Adjust the pressure by turning the pressure regulating
knob (2).
10. The unit is ready for use.
3
2
1
STARTUP
37

Publicité

Table des Matières
loading

Table des Matières